Photo Gallery - Page 1

Lot - Before

May 13, 2011 - Excavation

Excavation Complete

May 23, 2011 - Foundation, Emoltion, & Window Wells Complete

Jun. 17, 2011 - First Floor Framing

July 1, 2011 - Front of house

July 26, 2011 - Framing, Windows, Rough Plumbing, & HVAC Complete

Living Room

Master Bedroom

Master Bathroom

Master Bedroom / Bonus Room

Sep. 6, 2011

Kitchen

Master Bedroom

Master Bathroom

Bonus Rm / Office

Basement Family Rm

Bedroom

Basement Family Rm opposite view

Basement Bedroom

In Progress - Doors, Base, Case, Trim, Tile, Brick, Stucco, Garage Doors, & Paint.